ANR-963 Planning And Managing Lagoons For Dairy Waste Treatment
ANR-963, New August 1996. By Ted W. Tyson, Extension Agricultural Engineer,
Associate Professor, Agricultural Engineering, Auburn University.
Adapted from: Pfost, Donald, and Charles Fulhage. 1992. Lagoons
For Storage/Treatment Of Dairy Waste. University Extension. University
of Missouri-System, Columbia, MO.
Planning And Managing Lagoons For Dairy Waste Treatment
|
Dairy waste lagoons are earthen structures designed for biological
treatment and long-term storage of dairy waste. Lagoons are specially
constructed to prevent leakage of dairy waste to ground water.
The lagoon system allows manure to be handled with water-flushing
systems, sewer lines, pumps, and irrigation equipment. The natural
biological action on the waste results in less odor during land
application. Nitrogen content of the waste is reduced in lagoons
by as much as 80 percent. This reduction minimizes land area needed
for land application and enhances long-term storage.
I. Anaerobic Lagoons
Anaerobic lagoons look like farm ponds at first glance. They
are larger than manure storage basins, which do not provide significant
biological treatment or long storage periods, but smaller than
aerobic lagoons. Even though aerobic lagoons are designed to provide
a higher degree of treatment with less odor, anaerobic lagoons
decompose more organic matter per unit volume. Because of their
treatment and storage capabilities anaerobic lagoons are a good
compromise between storage basins and aerobic lagoons.
Anaerobic treatment of waste occurs without free oxygen to
liquefy or degrade high BOD (biochemical oxygen demand) organic
waste. With proper design and management the anaerobic lagoon
can function for years. odor from a well-designed and well-managed
lagoon will be only slightly musty; foul odor indicates a malfunction
requiring corrective action.
Advantages of anaerobic lagoon systems are:
- Manure can be handled with water flushing systems, sewer
lines, pumps, and irrigation equipment.
- The high degree of stabilization reduces odors during land
application.
- High nitrogen reduction minimizes the land area required
for liquid effluent disposal.
- Long-term storage is provided at low cost.
Disadvantages of anaerobic lagoons include:
- Public perception that a lagoon is an open container of manure.
- Offensive odors if improperly designed and maintained.
- Limited nitrogen availability if manure is used as a fertilizer.
II. Location Requirements
Ideally, lagoons should be located downslope from the dairy
freestall barn and milking center so that waste can be drained
or flushed to the lagoon by gravity. if scraping waste is practiced,
the lagoon should be relatively close to the freestall barn. With
a lagoon system, waste is usually flushed with recycled lagoon
water; therefore, flush system lagoons do not need to be located
quite so close to the dairy waste source.
Good engineering practice, as recommended in ASAE EP403.3,
calls for lagoons to be no less than 300 feet from any water supply
used for human consumption. Natural Resources Conservation Service
(NRCS) recommends 500 feet but will accept 150 feet from an upslope
well. Alabama Public Health Department, Division of Environmental
Programs Management (Milk Inspection), will not permit lagoons
to be closer than 100 feet from the water supply on a grade A
dairy.
Location of lagoons with respect to nonoperator-owned residences
is an important consideration. ASAE recommends a minimum distance
of 900 feet downwind. In Alabama, however, recommendations are
that lagoons be (1) located at least 1/4 mile from property lines
and nonoperator-owned residences and (2) screened from view with
a natural or constructed screen. In some situations, especially
in north Alabama, the location of a lagoon will be controlled
by soil and geological considerations.
III. Soils Investigation
Although printed county soil survey maps give general guidance,
the dairy operator planning a treatment lagoon should have an
on-site subsurface soils investigation made. Agencies with expertise
similar to the NRCS can conduct on-site soils investigations and
make appropriate recommendations. Soil borings or backhoe excavations
are standard procedures to identify shallow soil over coarse sand
and gravel, crevice, limestone, or permeable bedrock. If any of
these conditions exist, procedures and materials, such as clay
liners, geotextile liners, or concrete, to prevent seepage to
ground water must be used in construction.
NRCS currently offers this on-site soils and geologic investigation
assistance for animal waste management structures as part of the
animal waste management technical assistance program. They should
be contacted for assistance. This process will determine the soil
suitability for and final location of a dairy waste lagoon.
IV. Lagoon Design -- Volume
Proper design of an anaerobic lagoon requires the calculation
of volume that will be needed to accommodate waste accumulation
over the desired treatment period. Total lagoon volume of either
a one-stage or a two-stage system is composed of several parts
(see Figure 1):
- Treatment volume.
- Manure wastewater volume.
- Surface runoff volume.
- Net rainfall (rainfall minus surface evaporation, including
the 25-year-24-hour storm).
- Sludge volume.
- Freeboard volume.
Treatment volume provides enough dilution volume for
the breakdown of volatile solids by bacteria and is not removed
from the lagoon during pump-down operations. This volume is based
on the volatile solids daily loading rate in pounds per day per
thousand cubic feet. Typical recommended anaerobic lagoon loading
rate for dairy waste lagoons in Alabama ranges from 6 to 6.5 pounds
of volatile solids per thousand cubic feet per day. This is 1.5
cubic feet of permanent volume per pound of live dairy animal
weight. This amount can be reduced 20 to 35 percent for dairy
lagoon installations where solids separation facilities, which
are highly recommended, are in use.
Manure wastewater volume provides for wastewater storage
of the accumulated manure volume over the designed treatment period.
Pump-down interval and manure treatment period are the same and
should be 180 days in Alabama. Storage volume per pound of live
dairy animal weight is 0.5 cubic feet for 6 months. Longer treatment
time offers greater flexibility in scheduling pumping operations.
Surface runoff volume provides storage for rainfall
runoff plus any wash water or other freshwater that may be used
for cleaning buildings or lot areas. This volume is removed from
the lagoon during pumping operations. in Alabama, runoff from
open concrete areas can amount to a depth of more than 4 feet
per year over the entire surface. Reducing the area where runoff
drains directly into the lagoon will prevent unnecessary pumping.
Surface water, unless needed for filling or dilution, should be
diverted away from the lagoon. Generally the amount of rainfall
and runoff to be collected and stored in the lagoon is figured
on the wettest 10 years for net rainfall less evaporation on lagoon
surface plus berm runoff.
Net rainfall. The lagoon must provide storage for the
net gain of rainfall minus surface evaporation plus the berm area
runoff plus the 25-year-24-hour storm. In Alabama, typical annual
rainfall is at least 12 inches more than evaporates from a free
water surface. Dirt lot and berm runoff can also amount to as
much as 4 feet per year. This volume from rainfall less evaporation
is held in the second stage of a two-stage lagoon and removed
when the lagoon is pumped.
Sludge volume results from manure solids entering a
dairy lagoon and a portion remaining as bottom sludge. Research
indicates that approximately 0.19 cubic feet of sludge accumulates
per year per pound of total dairy cow liveweight adding manure
to the dairy lagoon. With solids separation, sludge accumulation
would be less. The sludge accumulation rate can be used to determine
volume necessary for sludge over any particular chosen design
time, most commonly from 12 to 15 years. Recommended sludge volume
is 0.5 cubic foot per pound of average dairy live weight.
Freeboard volume is the minimum extra depth above total
full pool level, usually 1 foot, after all other volume requirements
are met.
Figures 1 and 2 show a cross section of one- and two-stage
lagoon designs, which may be used throughout Alabama. Surface
area will vary with depth.
V. Two-Stage Lagoons
Where space is available, a two-stage lagoon should be constructed
to improve wastewater treatment and management flexibility. For
dairy operations that recycle lagoon liquid for open gutter flushing
where animals have direct access to flush water, a two-stage lagoon
provides some insurance against disease organisms being returned
from the first stage before a reasonable die-off period. in addition
to further treatment, the second stage also stores treated wastewater
for irrigation. This treated wastewater can be irrigated through
small diameter sprinkler nozzles.
The second stage should allow for a permanent volume that cannot
be pumped (2-foot minimum), wastewater volume for the waste treatment
period (180 days minimum), lot runoff volume for the desired treatment
period, net rainfall on both stages, and space for the 25-year-24-hour
storm for both stages (see Figure 2). The first stage will contain
only treatment (permanent) volume and sludge storage.
VI. Lagoon Design -- Geometry
Dairy waste lagoons can be designed in a variety of shapes.
However, circular or square lagoons allow easier mixing with propeller
or pump type agitators and are usually less expensive to construct.
When rectangular lagoons are constructed, a 4:1 length to width
ratio should not be exceeded to encourage even distribution of
manure.
Typical lagoon depths range from 8 to 20 feet, with a minimum
depth of 8 feet. The specific footage depends on animal numbers,
runoff area slope, and underground geology. Deeper lagoons offer
several advantages, including less land needed because of smaller
surface area requirement, more thorough mixing of lagoon contents
by rising gas bubbles, more efficient mechanical aeration, and
minimum odor.
The dike for a lagoon must be a minimum of 8 feet wide. Slopes
on earthen dikes and banks generally range between 2:1 and 3:1.
For good grass cover establishment and safe mowing, slopes of
3:1 or better are recommended. Generally, slopes below the waterline
are 2:1 though this depends on soil type and structure design.
An emergency spillway should be provided to protect the dam
in case of extreme flooding. The spillway should be placed a minimum
of 1 foot below the top of the berm, and allowance for settling
should be made. It should also be located as close to natural
ground level as possible and as far as possible from a corner
location. The spillway is intended for use in flood conditions
and is not to be used as a drain instead of pumping down the lagoon.
VII. Construction
Techniques
Proper lagoon construction is essential to ensure protection
of ground water resources as well as to provide a system that
will operate effectively for many years. Most guidelines for accepted
lagoon construction techniques include:
- Site preparation.
- Excavation.
- Embankments.
- Cutoff trench.
- Sealing.
Site preparation requires that all trees, grass, and
organic material be removed. Topsoil should be stockpiled close
to the construction site for later placement on the top and exposed
sides to allow good establishment of grass. After stripping, the
foundation area should be prepared to bond with the fill. Loose
dry material should be removed, and the foundation area scarified,
disked, adjusted for moisture, and compacted as necessary.
Excavation requires the removal of rocks, sand pockets,
gravel, and other materials not suitable for sealing. The excavation
should be deep enough for both proper volume and seal construction.
Lagoon embankments should be constructed to allow for
usual settling of 5 percent. The embankment should be planted
with a cover grass to prevent erosion and must be large enough
to accommodate mowers. Suitable fill materials should be free
of sand, roots, stones more than 6 inches in diameter, and other
objectionable material. The minimum moisture content of the fill
material and foundation should allow the formation of a ball that
will not separate when squeezed by hand. Experience has shown
that with suitable soil material (with enough clay content), three
passes of a sheepsfoot roller per 6-inch fill lift on the embankment
or bottom seal will provide adequate compaction for sealing.
A cutoff trench may be required to remove sand, gravel,
or other water-conducting materials to prevent leakage under the
embankment.
Sealing is required on the bottom and sides of the lagoon
to protect ground water. Seal construction guidelines generally
call for overexcavation and then backfilling and recompaction
of seal materials in thicknesses not exceeding 6 inches compacted
depth (not more than 9 inches deep for compaction).
The lower 6 inches of the bottom seal may be scarified and
compacted in place to eliminate removal and replacement. In general,
a minimum of 1-foot thick clay seal must be provided on the bottom
and sides of a lagoon. The deeper the lagoon, the thicker the
required seal, up to or beyond 4 feet for a water depth of 25
feet.
Some soils require soil amendments such as bentonite, soda
ash, or artificial liners to obtain a proper seal. Most properly
planned dairy waste lagoons receiving raw manure eventually seal,
limiting soil permeability to as little as 10^-6 cm/sec. Immediately
after construction, the lagoon seal should be covered with water
(at least 2 feet deep above the highest bottom elevation) to prevent
drying and cracking.
VIII. Solids Exclusion
And Agitation
Bedding, fibrous material, and some manure solids break down
very slowly or not at all in a lagoon. This nondegradable material
leads to excessive sludge buildup and to a crust forming on the
lagoon. Both sludge buildup and crust formation interfere with
the pump-out procedure. As much of these solids as possible should
be separated out of the manure waste stream and kept from entering
the lagoon. If not, over time the accumulated solids will reduce
waste treatment volume and cause "overloading" of the
lagoon. This "overloading" causes increased odor and
reduced waste treatment function.
As accumulated solids build up into the waste treatment volume,
they should be removed to prevent overloading by a special pump-out
procedure called lagoon renovation. This requires continuous
agitation with specially designed propeller or chopper pump agitators
during the pump-out procedure. For further information see Extension
Circular ANR-953, "Using Irrigation To Renovate Livestock
Lagoons. "
IX. Management Procedures
Proper management is essential to ensure that a lagoon functions
effectively and efficiently during its expected lifetime. Good
design and well-executed construction are worthless if the lagoon
is not properly managed.
For a lagoon system to operate successfully, start-up procedures
must be followed carefully. A new lagoon should be filled with
water to 60 percent of treatment volume before manure is introduced.
This assures sufficient dilution for the establishment of bacterial
activity and will also minimize start-up odors. Starting a lagoon
in late spring or early summer will allow a good bacterial population
to be established during the warm season.
After initial start-up, lagoons perform best when they are
loaded continuously. Flushing systems provide ideal loading conditions
for lagoons.
If foul odors develop in an anaerobic lagoon, the pH level
should be checked. A pH reading can be made using soil testing
equipment or litmus paper. The addition of hydrated lime will
increase a pH that is too low (less than 6.5). A higher pH will
increase the activity of methane bacteria and decrease the acid
concentration. If this treatment does not greatly reduce and control
foul odors, the lagoon is probably overloaded.
Lagoons usually fill to design capacity within 2 to 3 years
of start-up with the accumulation of wastes and rainfall on the
open lagoon surface. To prevent lagoon overflow, excess lagoon
liquid should be applied to grassland, cropland, or woodland at
rates within the soil infiltration capacity and the fertilizer
requirement of the vegetation. Lagoons should be pumped during
the growing season to allow enough storage space for wastewater
accumulation through winter when crop growth and nutrient requirements
are low.
The lagoon liquid should be sampled and analyzed to determine
its nutrient content. Table 1 gives information
on average dairy lagoon liquid accumulation rates and estimated
available nutrient contents. Table 2 estimates
application rates and minimum land areas needed for dairy lagoon
liquid irrigation application for different crops.
Wastewater irrigation using regular irrigation equipment is
the easiest and most cost effective way to apply lagoon liquid
to land. Irrigate lagoon liquid on days with low humidity and
when winds are not blowing toward neighboring residences. Irrigating
in the early morning and early in the week will reduce offensive
odors.
For more information on land applying dairy waste from lagoons
refer to Extension Circular ANR-925, "Calibrating Traveling
Guns For Slurry Irrigation." Procedures described apply to
wastewater irrigation from lagoons.
As lagoons age, salt concentrations may increase to level that
can inhibit bacterial activity. Salt levels in lagoons should
be monitored yearly to ensure they remain at safe levels. Electrical
conductivity (EC) is a convenient field measurement that indicates
salt content. Before the salt content reaches 2,000 to 3,000 milligrams
per liter (electrical conductivity of 3 to 5 millimhos per centimeter),
the lagoon should be pumped down and fresh water added. This will
reduce the chance of bacterial inhibition and the formation of
magnesium ammonium phosphate or struvite. This struvite may form
on the inside of pipes and pump impellers in the recycled flush
system, eventually causing breakdown. For information on addressing
this situation see Extension Circular ANR-860, "Controlling
Salt Buildup In Waste-water Recycling Systems."
Pumping operations should be started before the lagoon is full
to assure space (safety volume) is always available to hold a
25-year-24-hour storm. Good management guidelines call for pumping
the lagoon when the water level reaches 1 foot below the design
water level (usually marked by a treated post on the inside slope
of the last stage).
In a one-stage lagoon, permanent markers should be installed
(1) at a mark 1 foot below design water level to show when to
initiate pumping the lagoon and (2) at the lagoon treatment level
to indicate when to stop pumping (see Figure 1). In a two-stage
lagoon, a permanent marker is needed only in the second stage
to indicate when to initiate pumping. Pumping out too much effluent
is not a problem in the second stage if the 2-foot minimum depth
remains to allow recycle pump operation (see Figure 2). The first
stage is pumped only to remove accumulated solids which reduce
permanent treatment volume (lagoon renovation, once every 5 to
20 years, depending on design).
Table 1. Fertilizer Nutrients In Dairy Lagoon Liquid.
Total Anaerobic Lagoon
Liquid Capacity,
Ft^3/Cow |
Total Lagoon Liquid
To Be Irrigated*/Cow/Year |
Plant Nutrient |
Total Nutrients |
Plant Available Nutrients** |
| Irrigated |
Soil Incorporated |
| One Stage |
Two-Stage 1st + 2nd |
Gallons |
Acre-Inch |
Lbs./ Acre-Inch |
Lbs./ Acre-Inch |
Lbs./ Cow/ Year |
Lbs./ Acre-Inch |
Lbs./ Cow/ Year |
| 4,200 |
2,100 + 2,100 |
9,308 |
0.34 |
N
P2O5
K2O |
137
77
195 |
69
54
146 |
24
19
50 |
96
67
156 |
33
21
53 |
* Estimated total lagoon liquid
includes total liquid manure plus average lagoon surface rainfall
surplus; does not account for seepage.
** Irrigated: sprinkler irrigated liquid, uncovered for 1 month
or longer.
Soil incorporated: sprinkler irrigated liquid, plowed or disked
into soil within 2 days. |
Table 2. Land Application Rate For Irrigated Dairy
Lagoon Liquid.*
| Rate-Limiting Nutrient |
Cereal Grain |
Corn |
Fescue** |
Tifton44** |
Tifton44 Bermuda*** |
Bermuda Hay |
| Maximum Pounds Per Acre Per Year |
N
P2O5
K2O |
100
50
80 |
150
60
100 |
200
75
100 |
275
75
225 |
325
85
260 |
400
100
300 |
| Inches Per Acre Per Year |
N
P2O5
K2O |
1.4
0.9
0.5 |
2.20
1.20
0.68 |
2.90
1.40
0.68 |
4.00
1.40
1.54 |
4.7
1.6
1.8 |
5.8
7.4
2.0 |
| Minimum Acres Per Cow |
N
P2O5
K2O |
0.24
0.38
0.68 |
0.16
0.32
0.50 |
0.12
0.25
0.50 |
0.09
0.25
0.22 |
0.07
0.22
0.19 |
0.06
0.19
0.17 |
* N leaching and dentrification
and P2O5 soil immobilization unaccounted
for.
** Open grazing.
*** Controlled grazing. |
X. Appearance And Safety
A dairy waste lagoon should be as aesthetically pleasing as
possible. Berms and embankments should have good grass cover for
appearance and erosion control and be mowed and maintained on
a regular basis. A well-maintained lagoon is less likely to attract
attention and cause controversy. A fence should be provided to
prevent access by children, trespassers, and livestock. Warning
signs (SEWAGE TREATMENT FACILITY -- KEEP OUT) should be posted
and any access gate locked.
XI. References
Agricultural Waste Management Field Handbook. 1992. Part 651,
National Engineering Handbook. Soil Conservation Service.
ASAE Engineering Practice: ASAE EP403.3. Design Of Anaerobic
Lagoons For Animal Waste Management. ASAE Standards, 1996. St.
Joseph, Missouri.
Barker, James C. 1995. Lagoon Design And Management For Livestock
Waste Treatment And Storage. Circular EBAE 103-83. North Carolina
Cooperative Extension Service. NC State University, Raleigh, North
Carolina.
Sweeten, John M. 1983. Dairy Manure Handling Systems And Equipment.
Circular B1446. Texas Agricultural Extension Service. Texas A&M
University System, College Station, Texas.
Printed by the Alabama Cooperative
Extension System in cooperation with the Alabama Department of
Environmental Management and the Environmental Protection Agency
with Clean Water Act Section 319 Demonstration Funds. For more information, call your county Extension office.
Look in your telephone directory under your county's name to find
the number.
For more information, contact your county Extension office. Visit http://www.aces.edu/counties or look in your telephone directory under your county's name to find contact information.
Issued in furtherance of Cooperative Extension work in agriculture and
home economics, Acts of May 8 and June 30, 1914, and other related
acts, in cooperation with the U.S. Department of Agriculture. The Alabama
Cooperative Extension System (Alabama A&M University and Auburn
University) offers educational programs, materials, and equal
opportunity employment to all people without regard to race, color,
national origin, religion, sex, age, veteran status, or disability.
|
If you have problems loading
this document, please email publications@aces.edu
for assistance.
Publications Homepage | ACES Homepage
|