ANR-827 Water Harvesting For Irrigation: Developing An Adequate Water Supply
ANR-827, New May 1994. Larry
Curtis, Extension Agricultural Engineer,
Professor, and Eugene Rochester,
former Associate Professor both in Agricultural Engineering
at Auburn University.
Water Harvesting for Irrigation:
Developing an Adequate Water Supply
|
Alabama farmers are becoming increasingly aware of irrigation
as a tool for optimizing production. When all other management
practices are carried out efficiently, irrigation can help the
farmer achieve the top yields and quality demanded in today's
markets.
However, many farmers have been unable to irrigate because
they lack an adequate water source. Surface water sources, such
as streams, often do not have sufficient flow during the growing
season to provide irrigation water. And, in many areas of Alabama,
ground water sources are either inadequate or impractical to develop
for irrigation.
An alternative approach to securing irrigation water is to
collect and store surface water during the off-season, when rainfall
and stream flows are high. This practice is called water harvesting.
Where direct pumping is not feasible, either from streams
or lakes or from wells, water harvesting can make irrigation possible
where it was previously impossible.
Traditional Water Use For Irrigation
The quantity of water needed for irrigation is significant.
Different crops have different water needs, and each irrigation
system should be designed to provide adequate water for the crop
to be irrigated. However, the minimum storage capacity for most
situations is 1 acre-foot of water stored (or available) for each
acre irrigated. One acre-foot is equivalent to 1 acre of water
1 foot deep. This quantity of water will ensure an adequate irrigation
water supply for most crops in all but the most extreme drought
conditions.
To get the needed water, about one-fourth of Alabama irrigators
use wells, while three-fourths use surface water sources. Readily
available surface water sources include spring-fed ponds or lakes
as well as streams that flow through or are adjacent to farms.
In addition, some farmers have constructed reservoirs on streams
crossing their farm property.
One serious limitation on the use of streams for irrigation
has been that most pumping takes place in June, July, and August,
when stream flows are at their lowest. As more farmers pump water
from the same stream, downstream flow diminishes to the point
that no further pumping for irrigation is possible. Also, detrimental
environmental effects to the stream are possible.
Most stream flows in Alabama are highest from January through
April. A reservoir built on an on-farm stream captures and holds
some of this winter and spring stream flow for use in the summer--this
is an example of water harvesting. However, this practice has
been limited in some areas of Alabama for two reasons:
- Many streams are not located on drainage basins with topography
suitable for reservoir construction.
- Stream flows are often so high during the maximum run-off
periods that dams of the size and complexity needed are not economically
feasible.
As a result of all these factors, many locations in Alabama
lack sufficient water for irrigation at the time it is needed,
even though adequate water is available on an annual basis.
Harvesting Winter-Spring Runoff
One way to greatly expand irrigation capability in Alabama
is to build reservoirs that are not on primary drainage basins
but are located off-stream, either on smaller drainage basins
or on other land with terrain suitable for building water storage
facilities.
The simplest example of this is a case where a large creek
or stream flows by a farm, and a drainage basin leading into that
creek has a site that would hold enough water to irrigate the
farm if a dam were built across it. This drainage basin need not
be able to fill the reservoir on its own. Water can be pumped
from the large creek or stream into the reservoir during the winter
and spring, filling it and saving the water for summer use. This
practice is feasible and has already been put into effect at some
sites in Alabama.
A more difficult case is the situation where there is no suitable
off-stream drainage basin that can be dammed in the traditional
way to provide storage for an adequate quantity of water. In this
case a non-traditional type of reservoir is called for. A good
example of this type is a hillside reservoir where an earth embankment
is constructed on two or three sides, or in a curved shape, to
hold the desired amount of water. Again, water can be pumped from
the nearby stream in winter and spring to fill the reservoir.
Some recharge from natural drainage can be expected, depending
on site topography, but this is likely to be slight.
The most extreme case would be a circular or four-sided reservoir
built on essentially flat land. This is the most expensive reservoir
to build and would depend entirely on pumping from the nearby
stream, as there would be practically no natural recharge.
Design and Construction of Reservoirs
Determining design feasibility and construction and equipment
details requires careful analysis of characteristics of both the
site and the stream to be used. Site terrain must be suitable
for construction of a reservoir large enough to store at least
1 acre-foot of water for each acre to be irrigated. The stream
must provide enough excess water to fill the reservoir.
Topographic maps should be used to evaluate the site terrain
and identify the most suitable area for reservoir construction.
An engineering evaluation of the site is required to assess the
permeability of the soil to determine whether a clay or plastic
liner will be needed to prevent excess loss due to seepage. The
engineering analysis also covers construction requirements, including
the following:
- The amount of land clearing and excavation required.
- The type and nature of a cutoff trench needed to prevent
seepage.
- The availability of and feasibility of moving clay or other
suitable soil material into the cutoff trench.
- The nature of the embankment (height, top width, side slopes,
and total cubic yards required).
- The specifications for the spillway or overflow pipe, if
needed, and for drainage around the reservoir.
Design analysis must also consider the pump station and the
pipe line from the stream to the reservoir. Pump station requirements
will depend on the quantity of water pumped and the time for pumping.
For example, a pump station designed to fill the reservoir in
2 months must have twice the flow rate of a pump station designed
to fill the reservoir in 4 months.
The pipe line from the pump station to the reservoir is selected
based on the flow rate required to fill the reservoir in the specified
pumping time. Since pumping must take place during the high stream
flow conditions existing during winter months, the stream flow
should be carefully evaluated to determine a reasonable length
of time for the pump station to operate. The Alabama Geological
Survey has data and analytical methods for evaluating flows for
some streams in Alabama. Methods to better forecast water availability
from streams are being developed through research at Auburn University.
In some cases, stream flow will have to be estimated from personal
observation, with the advice of a consulting engineer. A good
estimate will require knowledge of the stream extending over several
years.
The figure below shows a typical water harvesting reservoir
and pumping station, with important features indicated. Table
1 indicates the number of days needed to fill reservoirs of varying
capacities at various typical pumping rates. See Table 2 for pump
horsepower requirements for various pumping situations.

Table 1. Days Required to Fill Reservoirs at
Various Pumping Rates.*
Reservoir Storage
Capacity |
Rate (gal. / min.) |
Acre-
Feet |
Gallons |
500 |
750 |
1,000 |
1,500 |
2,000 |
2,500 |
3,000 |
3,500 |
4,000 |
| 50 |
16,292,400 |
24 |
16 |
12 |
8 |
6 |
5 |
4 |
3 |
3 |
| 75 |
24,438,600 |
36 |
24 |
18 |
12 |
9 |
7 |
6 |
5 |
3 |
| 100 |
32,584,800 |
48 |
32 |
24 |
16 |
12 |
10 |
8 |
7 |
6 |
| 125 |
40,731,000 |
50 |
40 |
30 |
20 |
15 |
12 |
10 |
8 |
7 |
| 150 |
48,877,200 |
71 |
48 |
36 |
24 |
18 |
14 |
12 |
10 |
9 |
| 175 |
57,023,400 |
83 |
55 |
42 |
28 |
21 |
17 |
14 |
12 |
10 |
| 200 |
65,169,600 |
94 |
63 |
48 |
32 |
24 |
19 |
16 |
14 |
12 |
| 225 |
73,315,800 |
107 |
71 |
53 |
36 |
27 |
21 |
18 |
15 |
13 |
| 250 |
81,462,000 |
119 |
79 |
59 |
40 |
30 |
24 |
20 |
17 |
15 |
| 275 |
89,608,200 |
131 |
87 |
65 |
44 |
33 |
26 |
22 |
19 |
16 |
| 300 |
97,754,400 |
143 |
95 |
71 |
48 |
36 |
29 |
24 |
20 |
18 |
* Pumping time increased to allow for 5-percent losses to
seepage and other factors. Pumping time based on 24 hr. per day
operation.
|
Table 2. Horsepower Required to Deliver Designated
Flow Rates at Different Pumping Heads Based on 75-Percent Pump
Efficiency
Pumping Head*
Feet |
Rate (gal./min.) |
| 500 |
750 |
1,000 |
1,500 |
2,000 |
2,500 |
3,000 |
3,500 |
4,000 |
| 25 |
4.21 |
6.31 |
8.42 |
12.63 |
16.84 |
21.04 |
25.25 |
29.46 |
33.67 |
| 50 |
8.42 |
12.63 |
16.84 |
25.25 |
33.67 |
42.09 |
50.51 |
58.92 |
67.34 |
| 75 |
12.63 |
18.94 |
25.25 |
37.88 |
50.51 |
63.13 |
75.76 |
88.38 |
101.01 |
| 100 |
16.84 |
25.25 |
33.67 |
50.51 |
67.34 |
84.18 |
101.01 |
117.85 |
134.68 |
| 125 |
21.04 |
31.57 |
42.09 |
63.13 |
84.18 |
105.22 |
126.26 |
147.31 |
168.35 |
| 150 |
25.25 |
37.88 |
50.51 |
75.76 |
101.01 |
126.26 |
151.52 |
176.77 |
202.02 |
| 175 |
29.46 |
44.19 |
58.92 |
88.38 |
117.85 |
147.31 |
176.77 |
206.23 |
235.69 |
| 200 |
33.67 |
50.51 |
67.34 |
101.01 |
134.68 |
168.35 |
202.02 |
235.69 |
269.36 |
| 225 |
37.88 |
56.82 |
78.76 |
113.64 |
151.52 |
189.39 |
227.27 |
265.15 |
303.03 |
| 250 |
42.09 |
63.13 |
84.18 |
126.26 |
168.35 |
210.44 |
252.53 |
294.61 |
336.70 |
| 275 |
46.30 |
69.44 |
92.59 |
138.89 |
185.19 |
231.48 |
277.78 |
324.07 |
370.37 |
*Pumping head equals the elevation difference between the
water source and the reservoir plus friction losses in pipe and
fittings.
|
Cost Factors
Costs of water harvesting reservoir systems vary greatly, as
local contractor prices differ from one area to another. However,
costs will usually depend primarily on site conditions. Topography
dictates the length and height of the embankment, the area to
be cleared, and the spillway size. Geology will establish embankment
side slopes, cutoff trench dimensions, and the need for possible
reservoir sealing. The desired storage capacity establishes the
reservoir dimensions and pumping requirements, which in turn relate
to cost.
The costs cited in the following paragraphs are typical averages
for Alabama in 1994. Your actual costs may vary.
For a typical simplest-case embankment-type structure, a cost
range of $400 to $600 per acre-foot of storage can be expected.
Two- and three-sided structures will be slightly higher. Four-sided
or levee type structures are most expensive. Costs can be held
down by excavating embankment material from the reservoir and
considering this volume as a portion of the desired storage capacity.
If the geology of the site requires the entire reservoir to be
sealed, this can drastically increase the total cost.
Some general guidelines for estimating costs of specific items
are as follows:
Land clearing costs for wooded areas usually range from
$ 500 to $ 1,000 per acre.
Embankment dams are often priced by the job, but costs
are usually figured in the range of $.75 to $1.25 per cubic yard
of earth fill.
Excavation for a cutoff trench or keyway is similarly
priced, averaging $ 1.00 per cubic yard.
Overflow pipe can be roughly estimated at $ 1.00 per
inch of pipe diameter per running foot of pipe. The size and length
of the pipe will depend on the amount of water to be handled over
time. For a given drainage area, pipe size is based on runoff
storage available, drawdown time allowed, and emergency spillway
size. Materials can be new or used steel (solid or corrugated),
aluminum, plastic, or concrete.
Regeneration of vegetative cover on the embankment and
disturbed areas can cost from $200 per acre, if done by the owner,
to $1,000 or more per acre if contracted.
Pumping equipment and operating costs also vary, depending
on the site terrain, the size of the reservoir, and the time available
for filling the reservoir. Table 3 shows fuel requirements per
acre-foot to fill reservoirs at various elevations above the water
source.
Table 3. Estimated Diesel Fuel Required to Pump
1 Acre-Foot of Water at Different Pumping Heads.
Pumping Head*
Feet |
Fuel Required**
Gallons |
| 25 |
2.88 |
| 50 |
5.76 |
| 75 |
8.64 |
| 100 |
11.52 |
| 125 |
14.41 |
| 150 |
17.29 |
| 175 |
20.17 |
| 200 |
23.05 |
| 225 |
25.93 |
| 250 |
28.81 |
| 275 |
31.69 |
*Pumping head equals the elevation difference between the
water source and the reservoir plus friction losses in pipe and
fittings.
**Assumes 75-percent pump efficiency, 5-percent additional water
pumped, and 16.66 horsepower-hours per gallon of diesel fuel.
|
Is Water Harvesting for You?
If you already grow or would like to begin growing irrigated
crops, you should first investigate pumping from available surface
water or drilling a well if surface water is inadequate. These
sources usually provide cheaper water than does water harvesting.
If neither of these water sources is feasible, however, you should
investigate water harvesting.
Whether a water harvesting system can pay off for you will
depend on the added returns expected from irrigation. Because
of the scale and cost of a water harvesting program, you should
thoroughly research and plan your project, considering both engineering
feasibility and costs, before making any commitment. You may need
the services of a consulting engineer.
Another factor to be considered is that the Alabama Water Resources
Act of 1993 established an Office of Water Resources, with authority
to regulate all large-scale water use in the state, including
irrigation. However, details of implementation of the new law
were unclear as of the date of this publication. For more information,
contact
The Office of Water Resources
Alabama Department of Economic and Community Affairs
P.O. Box 5690
Montgomery, AL 36103-5690.
For further technical information and assistance, contact the
Alabama Geological Survey and the Soil Conservation Service. Your
county Extension agent also can help you find more information. For more information, call your county Extension office.
Look in your telephone directory under your county's name to find
the number.
For more information, contact your county Extension office. Visit http://www.aces.edu/counties or look in your telephone directory under your county's name to find contact information.
Issued in furtherance of Cooperative Extension work in agriculture and
home economics, Acts of May 8 and June 30, 1914, and other related
acts, in cooperation with the U.S. Department of Agriculture. The Alabama
Cooperative Extension System (Alabama A&M University and Auburn
University) offers educational programs, materials, and equal
opportunity employment to all people without regard to race, color,
national origin, religion, sex, age, veteran status, or disability.
|
If you have problems loading
this document, please email publications@aces.edu
for assistance.
Publications Homepage | ACES Homepage
|